Project Panthers: Student Activities Facilities Renovations

Student Activities Facilities Renovations:
One of the changes stakeholders can expect to see in our field house renovation are additional lockers for track and football. Due to the growth in both of these programs, it is common to have three student-athletes assigned to one locker.
Our nationally-recognized athletic training program will see a critical expansion to their treatment room. This area will be expanded from the current space of 360 square feet to over 3,000 square feet. The weight room will also see a much-need expansion.
The renovation projects will take place in phases with an estimated start date of March 2024 and continue through the summer of 2024.

April 2025 Update: COMPLETED
The field house renovation was completed in April 2025, and the updated facility is now fully in use. The project added much-needed locker space for our growing track and football programs, and the weight room received a significant upgrade, giving our student-athletes a modern, functional space to train.

Video of the renovated facility can be viewed at :41 seconds in the video below.
Our nationally recognized athletic training area also underwent a major expansion, growing from 360 square feet to more than 3,000. This renovated space now provides ample room for treatment, rehabilitation, and student-athlete care.



November 2024 Update:
Our administrators, principals, school board members, and partners from Kinco Constructors and Pinnacle Structures toured the ongoing fieldhouse renovations.



April 2024 Update:
Project Panthers is MOVING Forward! During Spring Break our crews tackled some of the renovations to the field house.
Turf has been removed and a new concrete pad poured to make way for a much-need expansion to the weight room.


Rubber floors and the weights will be installed this summer.

*Please Note - These are renderings or initial concepts and not necessarily the final designs.